Proceeding 27589 Register

Application status: Complete

Decision 27589-D01-2023 issued July 19, 2023

Watch an AUC hearing

Overview

The AUC has approved applications from Nova Solar G.P. Inc. to construct and operate the 150-megawatt Nova Solar Power Plant and associated Nova 1005S Substation. The project will be located on approximately 1,280 acres (518 hectares) of private, cultivated land in Wheatland County, Alberta, approximately two kilometres west of the hamlet of Carseland.

The AUC denied the associated applications for Transmission Line 927AL, to alter Transmission Line 927L, and to connect the power plant.

Further information about the proceeding is available through the AUC’s eFiling System under Proceeding 27589.

The eFiling System​

The eFiling System should be accessed to view the applications and the other documents the AUC will be considering in this proceeding. The system is also used to file submissions and evidence to participate in the proceeding.

To create an account, select “New account” and follow the steps to create a user ID and password. If you have any questions about how to use the system please contact us at info@auc.ab.ca or 310-4AUC.

Documents being considered in this proceeding can be found in the eFiling​ System (which requires log in). Once you have logged in, enter 27589 in the “go to” section at the top left corner of your screen.

Nova Solar Power Plant and Transmission Connection Project