The AUC is has approved applications from Solar Krafte Utilities Inc. to construct and operate a 60-megawatt solar power plant, designated as the Vauxhall Solar Farm, and the associated Solstice 549S Substation. The AUC issued Decision 27077-D01-2022 on December 16, 2022.

The project will be located on approximately 260 hectares of private land in the Municipal District of Taber and will be located approximately five kilometres northwest of the town of Vauxhall. Specifically, the project area will cover the following sections and as illustrated in the map below:

Section Township Range Meridian
NW17, W20, SW28, E29, E30, SE31 13 16 4

Vauxhall Solar Farm project location

The eFiling System

The eFiling System should be accessed to view the applications and the other documents the AUC considered in this proceeding. The system is also used to file submissions and evidence to participate in the proceeding.

To create an account, select “New account” and follow the steps to create a user ID and password. If you have any questions about how to use the system please contact us at info@auc.ab.ca or 310-4AUC.

Documents considered in this proceeding can be found in the eFiling System (which requires log in). Once you have logged in, enter 27077 in the “go to” section at the top left corner of your screen.

Vauxhall Solar Farm