Proceeding status: complete

Decision 27388-D01-2023, issued October 4, 2023

Watch an AUC hearing

Overview

In Alberta, four companies own and operate the province’s electric distribution system (ATCO Electric Ltd., Fortis Alberta Inc., ENMAX Power Corporation, and EPCOR Distribution & Transmission Inc.) and two for natural gas distribution (ATCO Gas and Pipelines Ltd., and Apex Utilities Inc.).

The AUC uses performance-based regulation when setting rates for these distribution utility companies to encourage efficiencies through providing incentives for reducing costs while at the same time safeguarding reliability of service. As a result, distribution utility rates are kept lower for customers than they may have been otherwise. The regulatory model reduces the regulatory burden of a traditional cost of service model involving scrutiny of numerous financial statements and promotes incentives for utility companies to become more cost-conscious and improve operational efficiencies.

The PBR3 plan approved in this decision builds upon the Commission’s prior PBR2 plan for the distribution utilities in effect from 2018 to 2022. The PBR3 plan parameters and specific approvals and modifications can be found in the decision.

The list of issues and specific items considered in this proceeding are included in Exhibit 27388-X0046 in the AUC’s eFiling System.

The eFiling System​

The eFiling System should be accessed to view the applications and the other documents the AUC considered in this proceeding. The system is also used to file submissions and evidence to participate in the proceeding.

To create an account, select “New account” and follow the steps to create a user ID and password. If you have any questions about how to use the system please contact us at info@auc.ab.ca or 310-4AUC.

Documents considered in this proceeding can be found in the eFiling​ System (which requires log in). Once you have logged in, enter 27388 in the “go to” section at the top left corner of your screen.

Third-generation performance-based regulation